Vessels for Saudi Aramco - Nuayyim
Field
Saudi Aramco, as the owner, contracted the Greece based J &
P to build a grass root plant aimed at processing additional 100
MBCD of crude oil from the Nuayyim Field South of Riyadh. MISA (AYTB's
Sister Company) was sub-contracted in 2006 to design and fabricate
the main processing unit of the plant. The unit comprises a Low
Pressure Production Tap (LPPT), a High Pressure Production Trap
(HPPT) and a Water Oil Separator (WOSEP). The unit is being transferred
to its final destinantion.
|
 |
Maintenance Project successfully completed revamp/re-tubing
of five Furnaces at Kemya during past few months.
Kemya is extremely pleased with our Safety, Quality & Schedule/Productivity
standards. |
 |
Technip Saudi Arabia sub-contracted
AYTB to construct the Olefins 1 Plant owned by Yanbu National Petrochemical
Company YANSAB. The scope of work consists mainly
of the following:
Piping , steel structure, mechanical erection in various operating
zones, Pre-commissioning as well as Reinstatement works.
Works are scheduled to be concluded March/April 2008 |
 |
Jubail United Petrochemical Company
awarded AYTB a contract to supply (Pipeline and Mechanical Works
including Electrical instruments) all adequate and competent labor,
supervision, tools, equipment, installed and consumable materials,
services, warehousing and each and every item of expense necessary
for engineering, procurement of materials, installation, construction,
handling, hauling, unloading and receiving, testing, quality assurance
and commissioning of Gylcol Transfer and Storage Expansion Project.
Works are scheduled to end Mid Sept.2007 |
 |
Ar-Razi Contracted AYTB to
execute similar works (Pipeline and Mechanical works) as described
above but without E/I. The project finishes Dec. 2007 |
AYTB NEWS HIGH LIGHTS: |
 |
AYTB was awarded recently a four years global
contract from SABIC for long term shut-down and maintenance support
services until 2011 as well as a five year global contract for supplementary
manpower services. |
 |
SABIC/Ibn Sina entrusted AYTB
for a five year maintenance support service until 2012. |
 |
SIPCHEM renewed its mechanical
support services contract with AYTB for one more year. |
 |
Multiserv extended its contract
with us for its slag handling operations at Hadeed for two more
years. |
 |
AYTB Kemya in-house team completed successfully
re-tubing/revamp of three ethylene furnaces; two more are underway. |
 |
QATAR PETROLEUM awards a contract
to AYTB Qatar Co. Ltd for the Engineering, Procurement, Installation
of modifications in the Dukhan fields |
 |
AYTB O&M Kemya Maintenance Project
successfully completed the retubing of seven ethylene cracking furnaces
well ahead of schedule, with no rework and no safety incidents.
|